RESIDENTIAL TOWER
DATE: 01/05/2018
Data given for
analysis:
·
RCC frame structure
·
Raft UG Tank
·
Two level basement
·
Ground + 22 floors residential tower
·
Per floor plate area is 500 sq mtr
·
23rd is terrace floor
s
Construction Area Estimation: 500 sqmtr x 25 floor = 12500 sqmtr
(approx.)
i.e.:
12500 sqmtr x 10.76 = 134500 sq
ft. (approx.)
Cost analysis:
1.
CONCRETE: (assume 2.5 per sqft)
Total
Quantity = 134500 x 2.5 = 336250 cubic ft = 9525 cubic mtr.
Total
Cost = 9525 x 8000 rs. = Rs. 7,62,00,000/-
2.
STEEL: (assume 6.5kg per sqft)
Total
Quantity = 134500 x 6.5 = 874250 kg = 874.3 tonne.
Total
Cost = 874.3 x 60000 rs. = Rs. 5,24,58,000/-
3.
BLOCK MASONRY, PLASTER AND WATERPROOFING:
(assume 450 Rs. per sq ft)
Total
Cost = 134500 x 450 rs. = Rs. 6,05,25,000/-
4.
EXCAVATION AND OTHER MISCILLENIOUS ACTIVITY:
(assume 200 Rs. per sq ft)
Total
Cost = 134500 x 200 rs. = Rs. 2,69,00,000/-
5.
LABOUR COST: (assume 400 Rs. per sq ft)
Total
Cost = 134500 x 400 rs. = Rs. 5,38,00,000/-
6.
INTERIOR COST: (assume 800 Rs. per sq ft)
Total
Cost = 134500 x 800 rs. = Rs. 10,76,00,000/-
7.
PASSENGER LIFT: (assume 150 Rs. per sq ft)
Total
Cost = 134500 x 150 rs. = Rs. 2,01,75,000/-
8.
FIRE FIGHTING SYSTEM: ( assume 100 Rs. per sq
ft)
Total
Cost = 134500 x 100 rs. = Rs. 1,34,50,000/-
TOTAL COST = Rs. 41,11,08,000/-
RATE PER SQ FT = 3057 Rs. per sq ft.
MATERIAL AND CONSTRUCTION METHOD SPECIFICATION
1.
CONCRETE:
·
The grade of concrete should be between M25 to
M40 grade.
·
Consider both RMC as well as site mix method for
pouring.
2.
STEEL:
·
FE500 grade of steel can be use.
·
Higher diameter of steel should be 36mm.
3.
BLOCK MASONARY, PLASTER AND WATERPROOFING WORK:
·
For masonry work consider light weight blocks of
100mm to 150mm width.
·
Apply sand face plastering on both external and
internal face of wall.
·
All wet areas are consider for waterproofing
work which includes bath, wc, kitchen sunk, balcony, chajja.
·
UG water tank and OH water tank is also include
in waterproofing activity.
·
Compound wall, storm water channel and ground
surface treatment is included in masonry work.
4.
EXCAVATION AND OTHER MISCELLANEOUS ACTIVITY:
·
Excavation from ground level to required final
foundation level using machine or manual as require on site conditions.
·
Pile breaking work.
·
Anchoring shore pile.
·
The surface below raft foundation should be
treat with proper waterproofing material such as Shahabad ladi or any
geotextile material.
·
Walls of lower and upper basement should be waterproof.
5.
LABOUR WORK:
·
Commercial plywood shuttering is considered for
concreting work.