Sunday, 26 August 2018

CHECKLIST OF CONSTRUCTION ACTIVITY

CONCRETE POUR CARD

Location               :                                                                               Date                         :
Grid level floor     :                                                                               Pour NO.                 :
                                                                                                              Drawing Reference :

Structure :  Slab / Column / Beam / Wall / Others  Describe ………..

Concrete Grade                                 :                                                 Start Time                 :
Coarse Aggregate ( nominal size)   :                                                 Expected end time   :
Concrete Quantity                            :
Construction Joint location              :

A
REINFORCEMENT
REQUIRED    
ACTUAL   
TOLERANCE
REMARKS
a.
b.
c.
d.
e.
f
g.
Cover
Cleaning
Spacing
Anchorage Length
Laps Dimension
Chairs
Stirrups


± 5mm – 2mm
Nil
±10mm

±10mm

B.
FORM WORK




a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
Shuttering Materials
Level – Slab / Beam Bottom
Beam / Column Dimension
Chamber / Slope
Electrical Inserts
Plumbing Inserts
Cutouts
Length / Height
Width / Thickness
Plumb
Tierod/Props as per approval









±5mm in 3000mm
±5mm in 3000mm

±5mm in 3000mm


a.
b.
LINES AND LEVELS
Top of Concrete Level
Top of shutter level



± 3mm
± 3mm


Approved / Not approved for concrete                                                  

Section Engineer                                                           Site Engineer     Const. Manager QA Engineer


Note : 
1.  Concrete must be cast against shuttered surfaces, a vertical stopper at construction joints must be provided.
2.  Construction joints must be defined, with in middle third of spans, considering rate & placement of concrete.



CHECK FOR MASONARY:

Project
Area / Building                  :
Description of Work / Dr :      

Date :
Time :


Required
Actual
Remarks
A
Specifications Check



1
Type of masonary – Brick  / Stone / Block



2
Ratio of motor cement : sand



B
Process Check



1
Marking of walls at Floor



2
Plumb Check Initial



3
Raking of Joints / Joint Thickness



4
Doors and Window Opening



5
Reduced levels of Sill/Lintel/Bottom



6
Plumb Check – Final




Remarks








Note : Record typical dimensional check on reverse of this format



Site Engineer



QA/QC Engr.



Client / Consultant





CHECKLIST FOR PLASTERING:



Required
Actual
Remarks
A
Specification Check



1
Type of plaster



2
Mix Proportion



3




B
Work Check



1
Plumb Marks



2
Correction of masonry ( if any)



3
Plaster Thickness



4
Base Coat



5
Finish to plane/ line (before initial set)



6
Doors and windows opening Check



7
Joint cut at straight line



8
Joint Finish



Approved / Not Approved


Remarks :










CHECKLIST FOR WATERPROOFING

SL. NO.
DESCRIPTION
OK
NOT OK
REMARKS
1
Surface Preparation / Surface Repair ( Removal of Dead Mortar



2
Leak check of concrete roof surface by ponding 2”-4” ( 72 hours)



3
Treatment of leakages by nozzle grout



4
Plastering with WP compoung of Spc. thickness



5
Slope check of plaster



6
Level Marks for Pressed tiles



Remarks







Checked by

Approved by




CHECKLIST OF PAINTING WORK:

Project
:


Area / Building
:
Date :

Description of work / Drg. Ref.
:




Required
Actual
1
Material as per approval


2.
Color Shade / Brand


3
Surface Preparation


4
No. of coat ( thickness in mm )


5
Coverage per m2


6
Curing if any


Approved for next coat / not approved for next coat




Remarks :













CHECKLIST FOR ROADWORK


Date                :

Location          :

Note Please tick each boxes and leave columns blank for items not applicable


SL. NO.
ITEMS TO CHECK
YES
NO
NA
REMARKS
1
Check for correct boundary line and diagonals




2
Check for correct layout marking of buildings & roadCheck if the area is cleared of bushes etc




3
Check sub grade levels as per drawings




4
Check any cross cabling / lines are cutting through road




5
Check for aggregate grading / thickness of layer




6
Check for number of passes of roller




7
Check for unfilled voids after watering




8
Check whether concreting is free from soil




10
Check concrete grade in case of concrete road




11
Check for proper expansion joint




12
Check for not disturbing the side drains curing rolling operations




13
Check for gradient and slope




14
Determine finished level of road / slopes




15
Checkout for all dead materials are cleared




Remarks



















No comments:

Post a Comment